Live Traffic Map

  

What's Happening Now

Construction Update - June 15, 2018

Asphalt base and new curb and gutter has been installed on the westbound High House Road approach. Grading has begun on the northbound High House Road approach and the asphalt base and curb and gutter is scheduled to be completed in two weeks. Grading will then progress to the eastbound High House Road approach. New fiber optic cable has been installed throughout the project area to run traffic signals and Town communications. This new cable is scheduled to be spliced into service during the week of June 18.

 IMG_2192

Construction Update - May 25, 2018

The switch over to the temporary signal on wooden poles has been completed and the existing metal poles have been removed. Installation of conduit for new fiber optic cable has begun. Road construction and AT&T utility relocation will resume on westbound High House Road after the holiday. Please remember to drive slowly and use caution while traveling through the intersection and surrounding areas.

Construction Update - May 14, 2018

Installation of the temporary signal is almost completed and it is expected to be activated within the week. Temporary lane closures throughout the intersection are still anticipated in order to remove the existing traffic signals and for installation of new fiber optic cable.

Temporary Signal

180509, Temp Signal