Overview (Spring 2008) The Town of Cary plans to extend Walker Street 1,200 feet from its current end at Cedar Street northwards to Chapel Hill Road. The project includes a grade-separated railroad crossing and realignment of cross streets. View maps of the proposed road extension area: Option 1 / Option 2 / Option 3 / Option 4 View renderings of the proposed extension: Image 1/ Image 2 / Image 3 / Image 4 Schedule
Cost Congressman David Price has set aside $980,000 of Federal Funds towards this project for the Town of Cary. The Town's Fiscal Year 2007 budget included $1.2 million for the preliminary planning of this project. The Fiscal Year 2008 Capital Improvements Plan indicates allocating an additional $1,050,000 in fiscal year 2009 and an additional $13,125,000 in fiscal year 2010 for easements and construction funding. Contact For questions, comments, or to see other information regarding this project contact:
|