PR10-12 Bids Chart

Cary Community Arts Center Bid Tabulation

Barnhill Contracting

C. T. Wilson Construction Co., Inc.

D.S. Simmons, Inc.

LeChase Construction Services

New Atlantic Contracting, Inc.

Riley Contracting Group

Rodgers Builders, Inc.

T. A. Loving Construction Co., Inc.

Base Bid

$9,400,000

$7,959,810

$7,847,700

$8,179,000

$7,780,000

$8,226,000

$7,819,000

$7,923,000

Alt. G-01

Delete Folding Partitions–Two Dressing Rooms, Classroom #2

($28,000)

($18,500)

($21,100)

($19,000)

($19,000)

($19,721)

($18,937)

($28,200)

Alt. G-02

Delete Reception Desk in Main Lobby

($18,000)

($12,597)

($11,400)

($17,000)

($17,000)

($18,070)

($28,067)

($17,400)

Alt. G-03

Omit All Casework

($103,000)

($115,639)

($116,800)

($103,000)

($104,000)

($109,121)

($162,184)

($129,000)

Alt. G-04

Omit Wood Floor and Depressed Slab in Rehearsal #1

($12,000)

($18,925)

($19,000)

($48,000)

($14,000)

($34,802)

($14,684)

($14,500)

Alt. G-05

Omit Pipe Grid and Attached Electrical Access Points in Rehearsal #1.

($6,000)

($11,850)

($14,800)

($5,000)

($25,000)

($17,928)

($17,000)

($16,700)

Alt. G-06

Omit Clerestory Windows and Lintels in Rehearsal #1.

($22,000)

($27,182)

($14,300)

($15,000)

($13,000)

($6,503)

($18,000)

($10,200)

Alt. G-07

Omit Operable Aluminum Windows, Provide Fixed Panel Windows

($25,000)

($25,500)

($18,000) *

($25,000)

($20,000)

($26,892)

($25,000)

($21,000)

Alt. G-08

Omit All Exterior Stainless Steel Rails; Provide Painted Steel Rails

($172,000)

($178,000)

($55,000)

($173,000)

($170,000)

($182,582)

($175,000)

($190,000)

Alt. G-09

Omit New Asphalt Shingles; Repair Existing Shingle Roofing

$6,000

($77,065)

($83,800)

($75,000)

($77,000)

($81,205)

($61,000)

($77,000)

Alt. G-10

Omit Building and Site Work Associated with New Outdoor Kiln Area

($6,000)

($24,994)

($23,800)

($26,000)

($17,000)

($22,037)

($26,000)

($41,200)

Alt. G-11

Omit Elevator #1, Equipment and Installation Only

($53,000)

($54,915)

($61,600)

($56,000)

($54,000)

($62,712)

($58,000)

($55,000)

Alt. G-12

Omit Construction for Storage at Stage/Crossover

($5,000)

($2,254)

($3,500)

($13,000)

($6,000)

$881

($4,000)

($6,000)

Alt. G-13

Provide Lighting Equipment by Owner-Preferred Manufacturer ETC.

$1,000

$0

$0

$0

$0

$1,568

$0

$0

Total of All Alternates

($443,000)

($567,421)

($425,100)

($575,000)

($536,000)

($579,124)

($607,872)

($606,200)

* Numeric text reads deduct of "18,000" but alphabetic text reads deduct of "eighteen thousand eight-hundred"