PR10-12 Bids Chart
|
Cary Community Arts Center Bid Tabulation | |||||||||
|
Barnhill Contracting |
C. T. Wilson Construction Co., Inc. |
D.S. Simmons, Inc. |
LeChase Construction Services |
New Atlantic Contracting, Inc. |
Riley Contracting Group |
Rodgers Builders, Inc. |
T. A. Loving Construction Co., Inc. | ||
|
Base Bid |
$9,400,000 |
$7,959,810 |
$7,847,700 |
$8,179,000 |
$7,780,000 |
$8,226,000 |
$7,819,000 |
$7,923,000 | |
|
Alt. G-01 |
Delete Folding Partitions–Two Dressing Rooms, Classroom #2 |
($28,000) |
($18,500) |
($21,100) |
($19,000) |
($19,000) |
($19,721) |
($18,937) |
($28,200) |
|
Alt. G-02 |
Delete Reception Desk in Main Lobby |
($18,000) |
($12,597) |
($11,400) |
($17,000) |
($17,000) |
($18,070) |
($28,067) |
($17,400) |
|
Alt. G-03 |
Omit All Casework |
($103,000) |
($115,639) |
($116,800) |
($103,000) |
($104,000) |
($109,121) |
($162,184) |
($129,000) |
|
Alt. G-04 |
Omit Wood Floor and Depressed Slab in Rehearsal #1 |
($12,000) |
($18,925) |
($19,000) |
($48,000) |
($14,000) |
($34,802) |
($14,684) |
($14,500) |
|
Alt. G-05 |
Omit Pipe Grid and Attached Electrical Access Points in Rehearsal #1. |
($6,000) |
($11,850) |
($14,800) |
($5,000) |
($25,000) |
($17,928) |
($17,000) |
($16,700) |
|
Alt. G-06 |
Omit Clerestory Windows and Lintels in Rehearsal #1. |
($22,000) |
($27,182) |
($14,300) |
($15,000) |
($13,000) |
($6,503) |
($18,000) |
($10,200) |
|
Alt. G-07 |
Omit Operable Aluminum Windows, Provide Fixed Panel Windows |
($25,000) |
($25,500) |
($18,000) * |
($25,000) |
($20,000) |
($26,892) |
($25,000) |
($21,000) |
|
Alt. G-08 |
Omit All Exterior Stainless Steel Rails; Provide Painted Steel Rails |
($172,000) |
($178,000) |
($55,000) |
($173,000) |
($170,000) |
($182,582) |
($175,000) |
($190,000) |
|
Alt. G-09 |
Omit New Asphalt Shingles; Repair Existing Shingle Roofing |
$6,000 |
($77,065) |
($83,800) |
($75,000) |
($77,000) |
($81,205) |
($61,000) |
($77,000) |
|
Alt. G-10 |
Omit Building and Site Work Associated with New Outdoor Kiln Area |
($6,000) |
($24,994) |
($23,800) |
($26,000) |
($17,000) |
($22,037) |
($26,000) |
($41,200) |
|
Alt. G-11 |
Omit Elevator #1, Equipment and Installation Only |
($53,000) |
($54,915) |
($61,600) |
($56,000) |
($54,000) |
($62,712) |
($58,000) |
($55,000) |
|
Alt. G-12 |
Omit Construction for Storage at Stage/Crossover |
($5,000) |
($2,254) |
($3,500) |
($13,000) |
($6,000) |
$881 |
($4,000) |
($6,000) |
|
Alt. G-13 |
Provide Lighting Equipment by Owner-Preferred Manufacturer ETC. |
$1,000 |
$0 |
$0 |
$0 |
$0 |
$1,568 |
$0 |
$0 |
|
Total of All Alternates |
($443,000) |
($567,421) |
($425,100) |
($575,000) |
($536,000) |
($579,124) |
($607,872) |
($606,200) | |
|
* Numeric text reads deduct of "18,000" but alphabetic text reads deduct of "eighteen thousand eight-hundred" | |||||||||