The Town of Cary plans to extend Walker Street 1,200 feet from its current end at Cedar Street northwards to Chapel Hill Road. The project includes a grade-separated railroad crossing and realignment of cross streets.
View a map of the selected alignment, option 2: Public Hearing Map
View maps of the proposed road extension area: Option 1 / Option 2 / Option 3 / Option 4
Public Involvement
November 2009 Community Information Workshop
View feedback.
March 2008 Community Information Workshop
View feedback.
TIGER II Discretionary Grant Program
The Town of Cary has applied for a Transportation Investments Generating Economic Recovery (TIGER) II Discretionary grant to fund the Walker Street Extension Project. Links to supporting documents as well as Letters of Support provided by project partners are provided below.
Supporting Documents
The Categorical Exclusion Environmental Document approved August 11,2010.
NCDOT approved the right of way drawings in the Location and Design Approval memorandum.
Federal Wage Rate Certificate
Detailed cost estimate at the 75% design.
Town of Cary Plans and Studies
The Town Center Area Plan (TCAP).
Bicycle and Pedestrian Plan
Downtown Streetscape Plan
Comprehensive Transportation Plan and associated Thoroughfare Map
Land Use Plan and Plan Map
Parks, Greenways & Bikeways Master Plan and PRCR Master Plan Map
Project Partners
-
North Carolina Congressional District 4 – Congressman David Price
-
North Carolina Congressional District 13 – Congressman Brad Miller
-
North Carolina Railroad
-
Capital Area MPO
-
Federal Railroad Administration
-
Federal Highway Administration
-
NCDOT
-
Norfolk Southern
-
CSX Transportation
-
Triangle Transit Authority
Letters of Support
Congressman David Price and Congressman David Millar have sent a letter of support to the Secretary of the USDOT.
The North Carolina Railroad is supportive of this project, and has offered to sponsor $1 million in private funding.
The North Carolina Capital Area Metropolitan Planning Organization (MPO) offered this letter of support.
The North Carolina Department of Transportation’s letter of support.
The Town of Cary’s letter of support.
A letter of support from Norfolk Southern railroad.
Triangle Transit provided a letter of support.
Schedule
|
|
Date |
|
Project Kick Off |
Summer 2007 |
|
Community Information Workshop No. 1 |
March 24, 2008 |
|
Community Information Workshop No. 2 |
November 10, 2009 |
|
Roadway & Structure Design complete |
Fall 2010 |
|
Right-of-way & easement acquisition complete |
Fall 2011 |
|
Construction begins |
Late Winter 2011 |
|
Construction ends |
Spring 2013 |
Cost
Congressman David Price has set aside $980,000 of federal funds towards this project for the Town of Cary. The Town's Fiscal Year 2007 budget included $1.2 million for the preliminary planning of this project. The Fiscal Year 2008 Capital Improvements Plan indicates allocating $1,050,000 in fiscal year 2009 and an additional $13,125,000 in fiscal year 2011 for easements and construction funding.
The Town of Cary Walker Street Extension will be funded by a combination of federal and local funds. Of the $28.7 million cost estimate, Town of Cary has previously secured $4.5 million in Federal grants, which consist of two federal earmarks supported by Congressman David Price (FFY 2008 appropriations - Sec. 129 Surface Transportation Projects - $980,000 and FFY 2009 appropriations - High Speed Rail Program Sec. 1103(f) - $1,104,000 and a Federal Surface Transportation Project – Direct Allocation (STP-DA) grant administered by the local MPO . The Town has committed $1.2 million of its own funds for design and engineering. The estimated project cost, less the Federal grants received previously and design and engineering services, is $22.2 million.
|
Fund Source Sponsor |
Type |
Amount ($) |
|
Federal Highway Administration (FHWA) |
FHWA - Section 129 |
$980,000 |
|
Federal Railroad Administration (FRA) |
FRA - Section 1103(f) |
$1,104,000 |
|
North Carolina Capital Area Metropolitan Planning Organization (CAMPO) |
Surface Transportation Program (STP-DA) |
$2,400,000 |
|
Total Grant Funding |
$4,484,000.00 |
The TIGER II grant request was submitted based on the net cost of the project. The grant program requires a local match of 20 percent that will be contributed by Town funds and NCRR.
Contact
For questions, comments, or to see other information regarding this project contact:
Eric Simpson, P.E.
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 380-4204
Eric.Simpson@townofcary.org
For information on Walker Street Extension Public Art, contact:
Denise Dickens
Public Art Coordinator
Parks, Recreation & Cultural Resources, Town of Cary
(919) 465-4791
denise.dickens@townofcary.org